26.4.14 Initial land deposit: Stockland Willowdale
12.5.14 Balance land deposit
22.5.14 land contracts exchanged
25.5.14 Initial deposit builder: McDonald Jones Homes
2.6.14 Deposit variation
5.6.14 Interim consolidated tender
26.6.14 Pre-selection walkthrough, colour studio
4.7.14 Preliminary plans received
10.7.14 Preliminary plans appointment
4.8.14 Main colour studio appointment
18.8.14 Contracts signed
10.11.14 Electrical appointment
11.11.14 Variation to contract - electrical modifications
11.3.15 Notification of upcoming land registration (2-4 weeks)
26.3.15 Land registered
15.4.15 Land Settlement
27.4.15 Soil tests and contour survey completed
27.4.15 Variation to contract (credit): upgraded H1 slab reverted to standard M class
30.4.15 BAL Certificate
8.5.15 BASIX and water board approval
13.5.15 Building approval application lodged (CDC)
28.5.15 CDC approval
28.5.15 Stage one 4% construction deposit paid
1.6.15 Authority to Commence Construction letter issued
3.6.15 On the construction list!
19.6.15 Site preparation
22.6.15 Piering
26.6.15 Slab complete
30.6.15 Progress payment 2 (slab completion)
11.7.15 Excess soil removed, Kordon termite barrier completed
13.7.15 Framing delivered
14.7.15 Framing commenced
18.7.15 Roof trusses
21.7.15 Framing completed
22.7.15 Progress payment 3 (framing completion)
23.7.15 Gutters and fascia
28.7.15 Windows, doors and doorframes in
31.7.15 Roof complete
10.8.15 Brickwork commenced
28.8.15 Electrical rough-ins
31 8.15 Pre-lining inspection
2.9.15 Eaves
3.9.15 Brickwork completed
7.9.15 Bricks cleaned
8.9.15 Insulation
10.9.15 Gyprocking commenced
21.9.15 Gyprocking completed
21.9.15 Carpenters onsite - skirting, architraves and doors. Garage door installed
22.9.15 kitchen installation and waterproofing
25.9.15 Pre-tiling inspection and fireplace installed
28.9.15 Tiling commenced
2.10.15 Tiling completed
2.10.15 Electrical commenced
9.10.15 Painting commenced
16.10.15 Painting completed
23 10.15 Plumbing and electrical, benches installed
31.10.15 Mirrors, shower screens
7.11.15 Splashback, door handles, flyscreens and flydoors
9.11.15 Fences down and site cleaned
10.11.15 Pre-PCI inspection
18.11.15 Bag and paint to columns and garage
20.11.15 PCI