Monday, 22 June 2015
Piering
Piering commenced today and we came in at 43 lineal
metres, under the allocation of 50 in our contract. Good to know we will get a
small refund and didn’t need to pay any extra. My husband went down to do the
piering inspection at 12pm and was told that plumbers will be onsite tomorrow,
and formwork is scheduled for Wednesday and Thursday if the weather is okay. If
everything goes to plan, our slab could be poured on Friday. I will be going
outside to do a sun dance I think as the weather is looking sketchy on
Wednesday and Thursday. Otherwise, we should have a slab next week.