Tuesday, 14 July 2015
Framing started
Got a call from our site supervisor this morning to advise that the frame carpenter was onsite and work has commenced. Framing should be completed by the end of the week and we should have a roof by the end of next week. Unfortunately there is a severe shortage of bricklayers, so there will be a 4-5 week delay with no activity after that. However, he is confident they will still finish before 18 December, quite possibly late November/early December.
Sunday, 12 July 2015
Ready for framing
Had a bit of an annoying end to the week dealing with an unreliable tradie who we had organised to remove our excess soil. Ryan our slab supervisor really helped us out and late on Friday afternoon we were able to lock in someone recommended by the builder to go out instead, first thing Saturday morning. 7am wake-up on a weekend was a shock to the system, but we were glad to get it all sorted. Framing will be on-site tomorrow (Monday) and we will move over to our site supervisor, Bernard.
Excess soil removed
Kordon termite barrier completed
Sunday, 28 June 2015
Starting to feel real now!
Slab from the front
Slab from the side with patio
our side yard which is approx 6m w at the front and 2m w at the back
Slab from the back
water tank space and 2m from boundary on this side
Back yard approx 4m. Not a lot but will be an alfresco/entertaining area
Friday, 26 June 2015
Tuesday, 23 June 2015
Completion date and site supervisor
We got a letter in the mail today from McDonald Jones introducing us to our building supervisor Bernard, who will be taking over from Ryan from frame stage until completion.
The other promising and freaky bit of information was that in line with our building contract, our home needs to be completed by 18th December, excluding allowable extensions for wet weather etc.
The reason this is rather freaky (but hopefully a good sign) is that the 18th December has been the exact date in my head as the absolute last day for handover, that will give us a spare 4-5 days to get our flooring done before Christmas closure. On the weekend we went down to the display home again (for the hundredth time) and when we mentioned we had just started building, one of the ladies in the office said we'd easily be in by Christmas. I'm not going to get my hopes up but there are lots of little signs that are making me feel that it won't be impossible!
The other promising and freaky bit of information was that in line with our building contract, our home needs to be completed by 18th December, excluding allowable extensions for wet weather etc.
The reason this is rather freaky (but hopefully a good sign) is that the 18th December has been the exact date in my head as the absolute last day for handover, that will give us a spare 4-5 days to get our flooring done before Christmas closure. On the weekend we went down to the display home again (for the hundredth time) and when we mentioned we had just started building, one of the ladies in the office said we'd easily be in by Christmas. I'm not going to get my hopes up but there are lots of little signs that are making me feel that it won't be impossible!
Monday, 22 June 2015
Piering
Piering commenced today and we came in at 43 lineal
metres, under the allocation of 50 in our contract. Good to know we will get a
small refund and didn’t need to pay any extra. My husband went down to do the
piering inspection at 12pm and was told that plumbers will be onsite tomorrow,
and formwork is scheduled for Wednesday and Thursday if the weather is okay. If
everything goes to plan, our slab could be poured on Friday. I will be going
outside to do a sun dance I think as the weather is looking sketchy on
Wednesday and Thursday. Otherwise, we should have a slab next week.
Saturday, 20 June 2015
Subscribe to: