Friday, 26 June 2015
Tuesday, 23 June 2015
Completion date and site supervisor
We got a letter in the mail today from McDonald Jones introducing us to our building supervisor Bernard, who will be taking over from Ryan from frame stage until completion.
The other promising and freaky bit of information was that in line with our building contract, our home needs to be completed by 18th December, excluding allowable extensions for wet weather etc.
The reason this is rather freaky (but hopefully a good sign) is that the 18th December has been the exact date in my head as the absolute last day for handover, that will give us a spare 4-5 days to get our flooring done before Christmas closure. On the weekend we went down to the display home again (for the hundredth time) and when we mentioned we had just started building, one of the ladies in the office said we'd easily be in by Christmas. I'm not going to get my hopes up but there are lots of little signs that are making me feel that it won't be impossible!
The other promising and freaky bit of information was that in line with our building contract, our home needs to be completed by 18th December, excluding allowable extensions for wet weather etc.
The reason this is rather freaky (but hopefully a good sign) is that the 18th December has been the exact date in my head as the absolute last day for handover, that will give us a spare 4-5 days to get our flooring done before Christmas closure. On the weekend we went down to the display home again (for the hundredth time) and when we mentioned we had just started building, one of the ladies in the office said we'd easily be in by Christmas. I'm not going to get my hopes up but there are lots of little signs that are making me feel that it won't be impossible!
Monday, 22 June 2015
Piering
Piering commenced today and we came in at 43 lineal
metres, under the allocation of 50 in our contract. Good to know we will get a
small refund and didn’t need to pay any extra. My husband went down to do the
piering inspection at 12pm and was told that plumbers will be onsite tomorrow,
and formwork is scheduled for Wednesday and Thursday if the weather is okay. If
everything goes to plan, our slab could be poured on Friday. I will be going
outside to do a sun dance I think as the weather is looking sketchy on
Wednesday and Thursday. Otherwise, we should have a slab next week.
Saturday, 20 June 2015
Sunday, 14 June 2015
Lights
The thought of committing to pendant lights has been haunting me for a good period of time now. We have been looking on and off for ages and today we made some decisions and purchases. Another thing to tick off the list! We also bought a wall-mounted clothesline (very exciting I know).
We already have downlights in the kitchen, living area and theatre but wanted to do pendants in the hall/entry and also some additional pendants to hang over the kitchen Island.
Below is the kitchen in the display home.
Below are the antique silver pendants for the entry and to run down the hall.
We already have downlights in the kitchen, living area and theatre but wanted to do pendants in the hall/entry and also some additional pendants to hang over the kitchen Island.
Below is the kitchen in the display home.
We have chosen 3 satin chrome tear drop pendants
Below are the antique silver pendants for the entry and to run down the hall.
Wednesday, 3 June 2015
Tuesday, 12 May 2015
Are we there yet?
We settled on our land on 15 April and since then it feels like everything is taking forever, when it really isn't.
We have had our contour survey, soil tests etc. completed. Had some good news that we would only need a standard M Class slab instead of the expected H1 for high salinity so happily received a credit for this. We then had to order a BAL Certificate that came back low and have been advised that we will be able to lodge a Complying Development Certificate (CDC) application which will save a lot of time (3 weeks as opposed to 6-8 for DA approval). We received our revised plans after BASIX and waterboard approval and are just awaiting the engineer's plans before we can lodge this week. Once approved, we hit the construction list! This can't come soon enough.
We visited the land on the weekend, our first visit since settlement. We got to see our official sold sign which was exciting. Even though it has been over a year since we secured the block, it has only officially been ours for a month now.
We have had our contour survey, soil tests etc. completed. Had some good news that we would only need a standard M Class slab instead of the expected H1 for high salinity so happily received a credit for this. We then had to order a BAL Certificate that came back low and have been advised that we will be able to lodge a Complying Development Certificate (CDC) application which will save a lot of time (3 weeks as opposed to 6-8 for DA approval). We received our revised plans after BASIX and waterboard approval and are just awaiting the engineer's plans before we can lodge this week. Once approved, we hit the construction list! This can't come soon enough.
We visited the land on the weekend, our first visit since settlement. We got to see our official sold sign which was exciting. Even though it has been over a year since we secured the block, it has only officially been ours for a month now.