Tuesday, 23 June 2015

Completion date and site supervisor

We got a letter in the mail today from McDonald Jones introducing us to our building supervisor Bernard, who will be taking over from Ryan from frame stage until completion.

The other promising and freaky bit of information was that in line with our building contract, our home needs to be completed by 18th December, excluding allowable extensions for wet weather etc.

The reason this is rather freaky (but hopefully a good sign) is that the 18th December has been the exact date in my head as the absolute last day for handover, that will give us a spare 4-5 days to get our flooring done before Christmas closure. On the weekend we went down to the display home again (for the hundredth time) and when we mentioned we had just started building, one of the ladies in the office said we'd easily be in by Christmas. I'm not going to get my hopes up but there are lots of little signs that are making me feel that it won't be impossible!

Monday, 22 June 2015

Piering

Piering commenced today and we came in at 43 lineal metres, under the allocation of 50 in our contract. Good to know we will get a small refund and didn’t need to pay any extra. My husband went down to do the piering inspection at 12pm and was told that plumbers will be onsite tomorrow, and formwork is scheduled for Wednesday and Thursday if the weather is okay. If everything goes to plan, our slab could be poured on Friday. I will be going outside to do a sun dance I think as the weather is looking sketchy on Wednesday and Thursday. Otherwise, we should have a slab next week.



Saturday, 20 June 2015

Site preparation

Site preparation is complete and piering is scheduled for Monday, pending the weather.



Sunday, 14 June 2015

Lights

The thought of committing to pendant lights has been haunting me for a good period of time now. We have been looking on and off for ages and today we made some decisions and purchases. Another thing to tick off the list! We also bought a wall-mounted clothesline (very exciting I know).

We already have downlights in the kitchen, living area and theatre but wanted to do pendants in the hall/entry and also some additional pendants to hang over the kitchen Island.

Below is the kitchen in the display home.


We have chosen 3 satin chrome tear drop pendants 

     

Below are the antique silver pendants for the entry and to run down the hall.



Wednesday, 3 June 2015

Let the construction begin!

We are officially on the construction list!!! Can't wait to see some progress.

Tuesday, 12 May 2015

Are we there yet?

We settled on our land on 15 April and since then it feels like everything is taking forever, when it really isn't.

We have had our contour survey, soil tests etc. completed. Had some good news that we would only need a standard M Class slab instead of the expected H1 for high salinity so happily received a credit for this. We then had to order a BAL Certificate that came back low and have been advised that we will be able to lodge a Complying Development Certificate (CDC) application which will save a lot of time (3 weeks as opposed to 6-8 for DA approval). We received our revised plans after BASIX and waterboard approval and are just awaiting the engineer's plans before we can lodge this week. Once approved, we hit the construction list! This can't come soon enough.

We visited the land on the weekend, our first visit since settlement. We got to see our official sold sign which was exciting. Even though it has been over a year since we secured the block, it has only officially been ours for a month now.




Thursday, 12 March 2015

Registration!

This week we FINALLY received the long awaited news that our land will be registering in 2-4 weeks. As soon as we register, settlement needs to take place within 14 days and then we give the green light to build! We are coming up to 11 months since we put down the deposit on the land. Even though we knew the timeframes and have been able to save, it has really really dragged on. I just need to see something on our land soon!

Once settled, we will be put on the construction list and work will commence within 20 working days. Our land was originally supposed to register in December to February, but this was delayed. Now I have my doubts that we will be in by the end of the year :( It will be tight, and my main concern is if we finish up in December, we might not be able to get our flooring done if it's close to Christmas and business closure period. November/December would also be the best time to move as it's a quieter time and easier to take leave. The public holidays help too! Shall see what happens...

On a happier note, we put down a deposit on some flooring on the weekend: coffee bamboo for most of the house and Godfrey Hirst eco+ carpet in clay path (bedrooms only). I am intrigued by this carpet which has a lifetime pet guarantee and can be cleaned with cold water only.












And here's our lucky number 13, now complete with council strip grass (plants will be in soon and pathways to come later).